2017
Early development phase
- Set-up of project team
- Location selection, size and design of the LNG import terminal
2018
Planning
- Design concept
- Port concept
- Simulations
- Regulatory affairs
- Preparation of approval procedure
2019–2023
Approval
- Implementation of approval procedure
- Invitation to tender and conclusion of agreements with general planners, plant manufacturers and other necessary contractual partners
2023–2027
Construction
- Sea port expansion and construction of the terminal
2027
Operation
- Regular operation of the terminal