Timeline

2017

Early development phase

  • Set-up of project team
  • Location selection, size and design of the LNG import terminal
2018

Planning

  • Design concept
  • Port concept
  • Simulations
  • Regulatory affairs
  • Preparation of approval procedure
2019–2023

Approval

  • Implementation of approval procedure
  • Invitation to tender and conclusion of agreements with general planners, plant manufacturers and other necessary contractual partners
2023–2026

Construction

  • Sea port expansion and construction of the terminal
2026

Operation

  • Regular operation of the terminal